KUDGI Super Thermal Power Plant

Boiler Primary and Secondary Structures - Karnataka, India

  • Client

    Doosan Power Systems India Pvt. Ltd.

  • Project Status

    Completed ( 2014 )

  • Tonnage

    1676

  • Partners

    Doosan Heavy Industries & Construction Co Ltd, Korea

  • Services

    Steel Procurement
    Fabrication, Supply
    Painting & Delivery of Structural Steel work to site

    • The project included Heavy Boiler Main and Auxiliary columns, Secondary structures, Bracings etc.
    • JSSL completed the trial assembly of main columns and used the multi coat paint system